SR2015 No 29: temporary storage on a flood plain of a main river
Standard rules for temporary storage on a flood plain of a main river.
Applies to England
Documents
Details
These rules allow you to store materials on a floodplain for up to 8 weeks. You must remove them after 8 weeks.
They do not allow you to store materials within:
- 8 metres of a flood defence
- 8 metres of a non-tidal river and 16 metres of a tidal river
All materials must be related to and stored adjacent to where specific works are carried out.
Materials must be stored parallel to the river bank and have a 1 metre break every 10 metres.