MOD publishes equipment plan and welcomes NAO report
The MOD has published its third annual update to the defence equipment plan.
![Astute class submarine HMS Ambush (library image) [Picture: Leading Airman (Photographer) Will Haigh, Crown copyright]](https://assets.publishing.service.gov.uk/media/5a60c975ed915d7dfea6733e/s300_45154670-g.jpg)
Astute class submarine HMS Ambush (library image)
An independent audit found the cost of the department鈥檚 11 biggest equipment programmes fell by 拢397 million in the past year.
The defence equipment plan is an annual update to Parliament on the MOD鈥檚 spending plans over the next decade.
The update sets out plans to spend around 拢163 billion on new equipment and support over the next 10 years.
The document sets out plans to spend around 拢40 billion on submarines, around 拢15.4 billion on land equipment such as tanks and armoured vehicles, and around 拢11.1 billion on helicopter capabilities.
Also today, the National Audit Office (NAO) has published its third assessment of the affordability of the equipment plan, which this year has been merged into one document with the MOD鈥檚 Major Projects Report.
Across the sample of projects that are reviewed by the Major Projects Report, this year represents the MOD鈥檚 best cost performance since 2005 and the best time performance since at least 2001.

A Royal Navy Merlin helicopter (library image) [Picture: Leading Airman (Photographer) Dave Jenkins, Crown copyright]
Minister for Defence Equipment, Support and Technology Philip Dunne said:
This equipment plan sets out our plans to spend around 拢163 billion on new equipment and support over the next 10 years.
For the third successive year it is realistic and affordable and provides excellent value for money to the taxpayer across the coming decade as evidenced by our success in securing savings in Equipment Support, which we have been able to factor in to the 10 year plan.
In addition I welcome the NAO report which recognises the progress we are continuing to make.
We have reduced costs by almost 拢400 million in our major projects and enjoyed our best performance on cost since 2005 and time since 2001.
There is always more we can do, but I am delighted the great strides the department has made have been recognised.
The Government had to take difficult decisions to balance the Defence budget as part of its long term economic plan, and this is what has led to a position where it is now able to invest significantly in equipment.
The NAO report recognises the progress we are continuing to make, including the relative stability of forecast project costs, as well as highlighting areas where we must continue to improve and refine our processes.
In order to ensure we have the flexibility to meet any unexpected costs, the MOD retains a central contingency provision of 拢4.6 billion over 10 years and around 拢8 billion of additional headroom in the later years of the decade.
Today鈥檚 report builds on Lord Levene鈥檚 Defence Reform findings published in December last year which said the right attitudes and behaviours are increasingly in place in the Head Office and the MOD鈥檚 management board has already come to be considered among the best in Whitehall.
The report also provided a positive assessment of progress in Defence Equipment and Support where reforms augur well for the future.